DEPAItTMENTOF ENERGY
OpE~TING E~ENSES ~ND C~IT.4L ACQUISITION
4
SCHEDULE 189
ADDITIONAL EXPLANATION FOR OPERATING OBLIGATIONS
EsER~
-.
.
Brookhaven National Laboratory
Laboratory
1. Contractor:
Associated Universities, Inc.
GK-}!ulti-Resource
Mission Resource
Task No.:
Contract No.:
EY-76-C-02-0016
189
2. Project Title:
NO.:
Surveillance of Facilities and Sites--SUMMARY
3.
GK-01-01-52-3
5.
4. Date Prepared:
Budget Activity No.:
March 1978
.
6. Working Location:
Method of Reporting:
See sub-activities
7.
Brookhaven National Laboratory
8. Project Term:
Person in Charge:
See sub-activities
Continuing
Principal Investigator:
From:
To:
See sub-activities
9. Person-Years:
FY 1978
Sciv,Res.Assoc.(Ph.D. or Equiv.)
Prof. (B.S. or Equiv.)
Sci. & Prof. - Total
Others
Guests & Research Collaborators
Total
10. Costs
Pres.Bud.
FY 1979
B.ev.Req.
FY 1979
7.0
x
2.0
_.K_LQ
2.5
---
3.0
2.0
---
3.5
4.0
3.0
4.0
4.5
5.0
7.5
7.0
Pres.Bud.
FY 1978
FY 1979
---
---
Rev.Req.
FY 1979
Labor (including benefits)
Mats., Trav., Dev.
Subcont., Spec’1 Proc.
Reactor, Accel., and/or
Computer Usage
Allocated Technical Services
Gen. & Adm. Overhead
Total Research Cost
150
211
425
Total Research Obligations
198
218
394
20
20
11. Reactor Concept:
1980
1.0
1.0
(In Thousands of Dollars):
Equipment Obligations
n
FY 1980
96
116
164
171
6
32
135
126
o
0
4
0
5;
5
117
1
47
11
.
12. Materials:
&
427
50