Cerna
KIRTLAND AFB
SUPPORT
F&SNO.
TITLE
19008
Electrical Power System
USER
|
STRUCTURE/FACILITY NO.
JTF
SCIENTIFIC STATION NO.
None
BOD
None
FOD
FUNDING
AGENCY
($000)
AEC
ENGR
PROC
CONST
FURN
PRE-GO
|
Costs Included in F&S No.
18001
COMPLETED
DESCRIPTION
A 750-kva substation (completed in 1964) lies west of the Trailer
Park onal2x18-ft. concrete slab.
A 12-ft. wide gateinthe enclosing 8-ft. high
‘chain link fence (with barbed wire outriggers) provides access to the 34 x 28-ft.
area.
Incoming overhead power is 4160 volt and 3 phase.
Outgoing power is fed to
Main Distribution Panel No. 1 (480 volt, 60 cycle, 3 phase) which, in turn,
feeds three secondary distribution components as follows:
Transformer and Distribution Panel No.
3 phase.
2:
225 kva, 480-208Y/120 volt,
Panel is 800 amp with a 4 wire bus.
Transformer and Distribution Panel No.
3:
Motor Generator and Distribution Panel No.
Similar to No.
2.
4.
The Motor Generator is 60 kw, 480-208Y/120 volt, 400 cycle, 3 phase
with a 400 amp,
120/208 volt, 3 phase bus.
General Area Power
1.
Two, Ikva, single phase, 480-120/240 volt transformers furnish
power to the simulator site.
2.
One,
3 kva,
single phase, 480-120/240 volt transformer furnishes
power to the guardhouse at the main gate.
3,
One,
3 kva,
single phase,
480-120/240 volt transformer furnishes
power to security lights and obstruction lights.
DRAWINGS:
VOL II
Spee
K-058-E1 thru E6
K-058-E13
19-4
aes!