6.14
SCHEDULE
The longest lead time item is considered to be the AN/TPQ-18 Radar.
The site preparation and utilities portion will be completed prior to
the arrival of the instrumentation,
The other systems will be installed
and checked-out during the installation and checkout time period of the
radar.
The integration for all of the systems will occur during the
time period noted for the radar.
AN/TPQ-18 Radar Schedule
Sept 66
1 Aug 65
|
Fabricate
|
|
Ship
Nov 66
|
| Install &
Checkout
Mar 67
|
May 67
|
| Sys.
Integration
Ops
Contract Let
Readiness Date
Due to the schedule, FY 66 funds must be provided for the
procurement of the systems.
-21-