eel
PART 1H, CHAPTERS 1 and 2

1.14

Detailed plans were made by H&N for

June

1958

provements to EPG was submitted in
in

two volumes entitled

LONG-

the same general title were completed during
FY’s 1957 and 1958. The remainder of the con-

E-7, TG 7.5, assisted by the OTO RadSafe Adviser and the AEC Rad-Safe
Officer, made detailed plans for TG 7.5 RadSafe operations and supervised their execution.
This planning included the use of IBM equip-

struction as then planned, together with addi-

tional requirements, forms the basis of the new
report which augments
through FY 1962.

long-range

planning

CHAPTER 2
PERSONNEL PHASING
struction and support requirements.

Construction personnel recruitment fell below

estimated rates in 1957. (See Fig. 3-1). This re-

duced manpower requirement was caused by
rescheduling the construction program.

2.2

Due to recruitment difficulties, it became
necessary to work engineering and criti-

cal craft personnel up to 84 hours per week during peak activity periods. This factor. together
with

the extended build-up period.

held the

2.3

Personnel of Task Groups supported by
TG 7.5 exceeded scheduled numbers by

approximately 150 and reached a_ peak of
2330 on 14 Mav 1958. The personnel build-up

A

TG 7.5 manpower was phased with con-

in advance of original predictions but reached
the peak as scheduled. The reduction of personnel of the various Task Groups was gradual,
until after the cancellation of the UN event when
numbers were reduced sharply.

a

24

of Task Groups supported by TG 7.5 was slightlv

TG 7.5 population below the estimated peaks.
TG 7.5 population fell off sharply during the

2.4

ber of events scheduled ard additional construc-

tion requirements. Another factor affecting the

strength. It was planned that TG 7.5 strength
would be reduced to approximately 1200 by 1

VHA events from Bikini to Johnston Island.
TG 7.5 peak population at Johnston Island was

suming a normal 18-month interim period.

latter part of April but remained higher than
originally planned due to an increase in the num-

TG 7.5 population level was the transfer of the
380 on 12 July 1958.
Page 40

‘

jects described in the June 1956 publication of .-

i?

1.15

of its own personnel.

|

off-atoll operations. hostile action alerts, natural
disaster defense, and for the radiological safety

and management of camp and support facilities,

*
\

‘

<A revised long-range plan for PAC im-

‘

1.18

RANGE IMPROVEMENT PLANNING—1959
THROUGH 1962 — ENIWETOK PROVING
GROUND. Volume I covers Site Elmer; Volume *
If covers Sites Fred and Rex. Some of the pro--

the recruitment of personnel, oreration

\>

plete by 1 October 1958.

\

completion of

construction prior to the beginning of the Operation.
‘

‘

concluded in time to permit

roll-up was completed on 16 September 1958.
The roll-up of Johnston Island began on 14
August end was completed by 19 September
1958. Eniwetok Atoll roll-up was essentially comfh an

Washington, D. C. After considerable delay, per-

mission was granted and a lease agreement was

Stations began on 26 July with the departure of
the LST-618 for Nauru, and Weather Station

7

obtain permission from the Australian Government, through the U. S. State Department,

Plans were also made for the roll-up of
the EPG and off-atoll Weather, RadSafe Stations after the completion of Operation
HARDTACK.The roll-up of Bikini Atoll began
after the JUNIPER event and was completed on
19 August. The roll-up of the off-atoll Weather

a

lian Administrator, Nauru, Central Pacific Islands. For entry to Nauru, it was necessary to

1.17

a

missioner, Trust Territories, Pacific; the British
Resident Commissioner, Tarawa: and the Austra-

and included in the TG 7.5 SOP.

a

AEC, handled the negotiations for sites and
clearances directly with the U. S. High Com-

TG 7.5 natural disaster defense and
hostile action alert plans were prepared

With the completion of the HARDTACK,

Phase I, series, TG 7.5 began the roll-up
program and subsequently reduced personnel

October 1958. Plans also indicated that TG 7.5
interim strength would not fall below 900, as-

BEST AVAILASLE COPY

“v

construction of newfacilities at Utirik, Nauru,
Ponape, and Truk. The Chief, Eniwetok Branch,

1.16

Om

Plans for JTF-Seven Weather. Rad-Safe
Stations called for the re-activation of
stations at Rongerik, Kusaie, Ujelang. Rongelap,
Wotho, Kapingamarangi, and Tarawa and the

prepare accurate and rapid Rad-Safe

em

1.13

mn’ ‘+

tr. ord. Refer to Chapter XI for details on TG
~ 5 Rad-safe operations.

“=e

information on these operations, refer to Chapters III and IV.

Select target paragraph3