NON

PART f, CHAPTER 6

6.1

DMA,in a letter to LASL cn 22 March
1958, first questioned the propriety of
detonating two atomic devices over EPG for the
ABMAprogram (sponsored by DOD). Innumerable conferences and voluminous correspondence
amongall elements of the HARDTACKorganization preceded the decision in early April 1958
to abandon the Site How ABMA launchingsite
(substantially. completed on 6 April 1958) and
to relocate the facilities on Johnston Island.
6.2

Following the official notification on 10
April 1958 that facilities would be moved from Site How to Johnston Island, numerous
conferences were held among all participants in
the ABMA program to determine the scope of
activity. Since the Users were at EPG, H&N
performed all engineering design at Site Elmer.

t was determined that engineering design could

be most efficiently expedited at EPG using engineering personnel who were cognizant of
ABMA program problems experienced at the
Site How installation.
6.3.

An inspection of the utilities at Johnston Island disclosed that most of them
were in need of repair; hence, extensive maintenance was performed prior to housing the full
complement of personnel required for the two
events scheduled there. Operation of all major
facilities at Johnston Island was assumed by
HEN prior to 13.May 1958.
6.4

The logistics problem was one of the
major difficulties encountered during the
construction build-up. The channel had to be
cleared of coral heads to permit entry by LST’s;
a coastal tug was secured from the Navy and
operated by an HEN crew, and a beaching ramp
was constructed for LST’s. In order to maintain
the anticipated construction schedule, it was
necessary to transship all existing equipment

Page 26
AFWL/HO

and materials from Site How to Johnston Island.
Procurement of additional scientific equipment
and materials from Honolulu and the Mainland
was also necessary, with shipments being made
in most instances by MATS and commercial
air freight to Honolulu for transshipment to
Johnston Island. During the construction period,

~

JOHNSTON ISLAND

~~

CHAPTER 6
SIGNIFICANT EVENTS

a total of 35,194 measurement tons (5580 long

tons) were received at Johnston Island by surface craft and 2,193,955 pounds by air.
6.5

A 60-hour extended work-week was required during the construction phase to
maintain the accelerated construction schedule.
scientific Station construction was initiated on
a 1958, and work continued at an accel- «
erated pace until the completion of all Scientific
Stations on 7 July 1958. Arrangements were

made with the Navy to secure from Hawaii —

various items of heavy

the Johnston Island p.

equipment required for

of Operation HARD-

TACK to avoid interference with progress ‘at
Eniwetok and Bikini Atolls. 6.6

The TEAKevent, originally scheduled for
firing from Site How on 23 April 1958,
was detonated over Johnston-Island on 31 July
1958. The ORANGEevent, originally scheduled
for firing from Site How on 7. May, was detonated over Johnston Island on 11‘ August.

REPATRIATION OF RONGELAP
NATIVES _
6.7

Between Operations REDWING and
HARDTACK,250 Rongelap natives were
transported from their temporary home at Ejit
Island, Majuro Atoll, and returned to newly constructed homes on Rongelap Atoll. Details of the
repatriation were published by H&N for the AEC
in a report entitled “Report of Repatriation of
the Rongelap People,” dated November 1957,
and distributed to all offices concemed.

$5

Select target paragraph3