SUPPORT: .
JOHNSTON ATOLL
02040
Page 2
a) On the south shore extending westward approximately 2,700-lin.
ft. from the western peninsula to a point south of the Test Command launchers.
b) Approximately 440-lin. ft. at the southwest corner.
c) On the west shore extending northward approximately 2, 050-lin.
ft. from the wharf to the LOX storage area.
d) On the north shore extending eastward approximately 3,000-lin.
ft. from a point north of Launch Pad No. 1 to a point north of the
warehousing area.
e) On the north shore approximately 140-lin. ft. north of Building
100, 270-lin. ft. on the Point House peninsula, 200-lin. ft.
north of the Power Plant and 1,200-lin. ft. around the wharfing
area.
f) Approximately 1,700-lin. ft. on Akau Island and 800-lin. ft. on
Hikina Island.
FY 1969
ENGINEERING Completed.
Drawings:
Naval Facilities Engineering Command Numbers:
1229668 thru 1229678
PROCUREMENT
Completed.
CONSTRUCTION Shoreline protection is presently being accomplished at
the following locations on Johnston Island:
a) Approximately 800-lin. ft. of concrete revetment on the westernmost unprotected section of the south shore.
b) Approximately 1,125-lin. ft. of concrete revetment on the northwest peninsula.
c) Approximately 700-lin. ft. of concrete revetment on the northeast
corner.
d) Approximately 250-lin. ft. east of and 180-lin. ft. west of the old
seaplane rampwith steel sheet piling capped with concrete.
2-4)
VOL I