SECTION 17
COMMUNICATIONS SYSTEMS
GENERAL CONDITIONS:
17-01.
The following paragraphs of Section 15 of these
specifications shall apply to this section: 15-01, 15-0e,
15-03 and 15-04.
The work to be done under this section of these
17-02.
specifications shall include the furnishing of all
materials, labor, equipment, and tools required to

complete and have ready for operation the installation
of the following items in accordance with these specifications and the applicable drawings:

D, E,

a.
Telephone System on and between Sites B, C,
L,M, N, P, Q@, R, S, @nd T.
bd.

Public Address System on Sites C, D, and E.

e.

Intercommunication System on Site B.

17-03.
The work to be done under this section of these
specifications shall also inlude the furnishing of all
labor, equipment, and tools required to install radio
transmitters and receivers.

TELEPHONE SWITCHBOARDS AND INSTRUMENTS:

17-04.

All Telephone Switchboards and Instruments shall

17-05.

The Switchboard for Site "B" shall be a two-

comply with the requirements of Specification No.
HN-7H-304 and Addendum #1.

position Kellogg Masterbuilt Junior Switchboard, or

equal wired and equipped for 220 common battery and

30 magneto lines.

It shall be complete with power

equipment, main distributing frame, and wire chief's
testing equipment.
17-06.

The Switchboards for Sites C,D, and E shall

each be @ Single-positionKellogg Masterbuilt Junior

Switchboard, or equal, wired and equipped for 45
common battery and 5 magneto lines.
Each shall be
complete with power equipment,
and test set.

17-1