SECTION 4
EARTHWORK FOR UTILITIES
4-01.

GENERAL REQUIREMENTS:

a.
This division of the work includes furnishing all labor, materials, and equipment required to

complete trench and related work outside of structures,

as required for the installation of all pipe, conduit
and other earth embedded utility lines as shown and as
specified elsewhere in these specifications.

b.
All work shall be coordinated with that of
the mechanical craftsmen concerned to the end that all

work is properly installed.
Depth and breadth of
excavations and slope and contour of trench bottoms
shall be as required for proper installation of the

utilities as specified in other divisions of these specifications or otherwise required, and as herein specified.
4-02,
WATER AND SHORING:
Excavations shall be kept free
of standing water andprotected as required to prevent

surface water run-off into them.
All shoring required
to protect the work shall be provided and maintained in
approved manner.

4-03.

EXCAVATION:
a.

Excavations

shall be of the open cut type.

Banks shall be cut as nearly vertical as possible,

Trench work shall not proceed until all compacted f111

is in place.

b.
Trenches to receive pipe, conduit, etc., shall
be excavated true to line and accurately sloped to drain
in accordance with the drawings and the requirements of
the mechanical tradesmen concerned.
Trenches shall be

of sufficient width to provide a clear space of not less

than 6 inches on either side of the pipe, and except as
otherwise directed, shall have a minimum width at the

bottom of 18 inches.

Where sheathing is required, the

trench widths shall be increased correspondingly.
ec.

Trench bottoms shall be dished out as required

for bedding bell and spigot and flanged pipe work to the

end that pipe rests for its entire length upon the bottom
of the trench.
The bottoms of all trenches for sanitary
Sewers shall be rounded so that at least one-third of

4-1

Select target paragraph3