IV-2

REPORTS:

Progress Charts - The Contractor shall witha.
in five (5) days after date of commencement of work pre-

pare and submit to the Contracting Officer for approval
a practicable schedule, showing the order in which he pro-

poses to carry on the work, the date on which he will

start the several salient features (including procurement
of materials, plant and equipment) and the contemplated

dates for completing the same.
The schedule shall be in
the form of a progress chart to indicate the percentage
completed at any time. The chart shall be corrected at
the end of each month and delivered to the Contracting

Officer,

bd.

Records and Books of Account - The Con-

tractor shall keép records and books of accounts at a

place mutually agreeable, showing the actual cost to it
of all items of labor, materials, equipment, supplies,
services, and other expenditures of whatever nature of

which reimbursement is authorized under the provisions of

this contract and as prescribed in Article VIII of the
contract.
As further prescribed in Article VIII, the
Commission shall at all reasonable times be afforded
access to such records and books of account.
¢.

Fiscal Reports - The Contractor shall

make such fiscal reports to the Commission with respect

to activities under this contract as the Commission may

require from time to time, such reports to be in the
form prescribed by the Commission.
ad.

Breakdown Estimate:

(1)

Prior to the execution of the contract

or modifications thereto, the Contractor shall submit to
and obtain approval of the Contracting Officer or his
duly authorized representative a breakdown estimate in

duplicate.

This breakdown estimate shall include indivi-

dual items and shall be in sufficient detail to show

approximate quantities and type, kind,

material and equipment involved.

character of work,

The individual quanti-

tles and cost estimates are approximate only and changes
may be requested in the work items by means of directives

without formal modification of the contract, except that
for changes which materially increase or decrease the
Scope of the work to be performed, there will be an adjustment in the payments to be made to the Contractor in accordance with Article XIII of the contract.