STANDARD OPERATING INSTRUCTIONS NO. 2
MAINTENANCE AND OPERATION INSTRUCTIONS FOR
POL FACILITIES PARRY ISLAND
valves V13 and 14 thence to the loading rack through valve
V1ll2 and quick opening valve V111i into tank truck.

A line also

supplies the powerhouse and laundry through valve V113.
During the unloading operation, valves V2 to V15 are
closed, and the required tank outlet valves, pump suction and
discharge valves, and valve V115 are opened,

After the truck

has been filled and the pumps cut off, valve V15 should be
opened to relieve the pressure on the system back into the
tanks.
NOTE:

Valve V15 must always be closed when a truck is

being loaded to prevent the pump from circulating the liquid
back through the tanks thus giving the wrong meter reading.

GASOLINE

LOADING OPERATION
Gasoline is delivered to the POL tank farm by tanker ship
which anchors off shore and connects to a flexible line at the
marker buoy.

This flexible line, in turn, is connected to a

steel submarine pipe which delivers the gasoline to Gasoline
Dehydrators Nos. 3 and 4 through valve V55, Strainer 5-2,
Pressure Regulator valve V56, and valves V57 and V58.

(Salt

water in the submarine line is drained back to the lagoon
through valve V114).

The entrained water is separated at the

dehydrators; the gasoline then goes to deaerator No, 2 through
valves V59 and V60, and Pilot operated motor valves V6l and Vé62,

2-5