and two water shots in the megaton yield ranze.

A smaller array extend-

ing to 15 miles was planned for the lower yield Echo shot.*

2e2

LAND AND LAGOON PHASE
The land and lagoon phase of operations toox plece at Bikini Atoll

for Shots 1, 2, 3, and 4 and at Eniwetok for Shot 6.
sive preparations for Echo were made at Eniwetok,

In addition exten-

The instrumentation

of the island and the lagoon raft stations is discussed in Chapter 3.
The preshot preparetions at 8ikini involved readying the e,uipment,
calibrating the instrmments, and emplacing them at the island ond lugoon
raft stations, This was completed a week prior to Shot 1. Final checks
were made on the equipment at all the existing stetions 1 to 2 days
before shot time to assure ccmplete readiness and operational efficiency.
rreparations were also made for the r-covery operations and for the

re-instrumentation of the stations.
Participation in all detonations except Shot 5 was achieved although
not to the extent originally planned. The lesser participation was due
to the destruction of equipment by the fire in the compound at Tare fci-~
lowing Shot 1, Tables G.1 through G.20, Appendix G, snow the degree of
instrumentation and recovery for each shot,

2.3 PHASE
Free~floating buoys were selected for sampling fallout in the open
ocean on the basis of their evalwtion at IVY// tach buoy station was
so located that it was expected to drift to the desired positicn by shot

time. Records were kept of the locations and times of placement and
recovery of each buoy. From these data, positions at shot time were

r

estimated by assuming that each buoy drifted in a straight line at a
constant speed, It was essential that the time the buoys were et sea be
held to a minimum so that their locetion at shot time could ve estimted

as accurately as possible,

For this reason the array for each test was

laid out within 36 hr of the proposed shot time snd recovered as soon as
possible afterwards,

Sea phase operaticns were mounted from Eniwetok Atoll for all shots.
Detailed direction, once Naval wits vere committed, was accomolished
from ships based at Bikini Atoll or from vessels actively participating
in Project 2.5a operations,
2.3.1

Pretest Freparetions

The buoys and asscelated equipment were assembled and tested at
Parry Island. Liaison was estublished with the Navel Tack Group and
plans for conducting the sea phase were made.

These plans consisted of

loeding two sea-going tugs with csuipment at Eniwetok Atoll, after which
the vecsels proceeded to sea to lay the buoys. After completion of the
buoy lcying operctions, the tugs retired to a safe area to await the
shot. Upon receipt of clearance from the Naval Task Group Commander
folloving the shot, the tugs proceeded to recover buoys after which they
returned to inivetok to off-load, Detailed plans for laying the buoys,
* Not fired,

28

ey

Select target paragraph3