QUAN. UNIT TOTAL COST STATION NO. II YVONNE (Continued ) "TOA DESCRIPTION OF PROPERTY UNITS 251 Heavy timber frame structure, 8'-0" x 4'-0" x approximately 8'-0" high mounted on a 8" wide x 5'-0" long x 4” thick concrete footings top and upper 4'-0" of sides covered with 1/2" extericr plywood; earth fill built up approximately 8'-0" from finish grade to top of struc- ture and out, sloping away at 1-1/2 to 1 maximum. Installed equipment: Each 1 - 5 KVA “Gregory” transformer, serial No. 5026231, H & N No. TR-59. (The above list does not contain any user-furnished or user-installed equipment. ) Construction Contract Cost Engineering Cost 1,219.08 187.87 1,406.95 STATION NO. 252 Consists of rehabilitation of Greenhouse Station 6B, including in- atallation of dehumidification units; lighting panel and safety awitches mounted on a 12'~O" x 6" x 6" electrical gutter with wiring for lights, power and Users equipment. Installed equipment: Each 1 "Kilpatrick" condensor dehumidification unit, Berial No. 331-D-122950-26, H & N No. A-128; 1 "Kilpatrick" evapora- equipment. ) Construction Contract Cost STI-k Engineering Cost 22,230.80 669.68 22,900.48 XIGNaddV tor dehumidification unit, serial No. 332-D-1-102750-23, H & N No. A-133-A; 6 - 25 KVA transformers. (The above list does not contain any user-furnished or user-installed