QUAN. UNIT II FLORA (Continued ) TOTAL COST “TTIOA OOT-L DESCRIPTION OF PROPERTY UNITS SUB-STATION NO. 2 Outdoor sub-station consisting of three transformers installed on a reinforced concrete pad 8'-0" x 3'-0" x 0'-6" thick; primary fuse cutouts and junction box mounted on a 9'-0" high unistrut tower; station enclosed by 52 lineal feet of 8'-0" high chain Link fence in- cluding a 3'-0" hinged gate, and grounded to a grid of #1/0 bare Each copper wire. Installed equipment: 2 - 10 KVA "Uptegraff" transformers, serial Nos. 58162, 58177, H & N Nos. TR-111, TR-113; 1 = 25 KVA "Uptegraff"” transformer, serial No. 5026314, H & N No. TR-189. (The above list does not contain any user-furnished or user- installed equipment. ) Construction Contract Cost 1,154.56 1,154.56 STATION NO. 3 One-story wood frame construction, 12'-8" x 8'-8" x 8'-4" mean height; Bides covered with 1/2" plywood; shed roof of composition roofing over 1" diagonal sheathing; constructed on concrete slab with perimeter footing 1°'-2" below grade; interior sprayed with vapor-seal; platform on roof for exhaust fan; complete with electrical wiring and fixtures; area 0.D. 110 square feet; volume 917 cubic feet. Installed equipment: Bach 1 - 400 CFM "Master Fan Corp.” exhaust fan, (The above list does not contain any user-furnished or user-installed equipment. ) | Construction Contract Cost Engineering Cost 7, 2h9.06 2, 388.96 9,638.02 XIGNGddvV Serial No. 02022, H& N No. F448,