II.
TIME TABLE FOR SEAREX.IN ENEWETAK
In keeping with the objectives of the entire SEAREX program, it is
necessary that we sample from the same experimental station during both a
wet and dry season.
For this reason it is necessary that we man the Enewetak
Tower during January-March 1979, the dry season, and July-September 1979,
the wet season. To meet this schedule, it will] be necessary to send a crew
of four people during the period of 2] November-20 December 1978 for the
purpose of constructing the tower and setting-up the experimental equipment.
Five people will be at the site during the wet and dry season experiments.
MPML has indicated that they will be able to house these people. Our schedule
is summarized below:
SEAREX TIME TABLE - ENEWETAK
EVENT
Site Construction
DATES
21 November 20 December 1978
NUMBER OF SCIENTISTS
4
Dry Season Flux Experiment
9 January 7 March 1979
5
Wet Season Flux Experiment
3 July 5 September 1979
5