CHAPTERI, SECTION 3

SECTION 3
CONTRACT HISTORY
Contract

AT(29-2)-20

was

modified

14

times during Operation HARDTACK. Other
changes were made in the basic contract and
Appendix B by the use of 25 approved Re-imbursement Authorizations. The contract as constituted for Operation HARDTACK, Phase I,
was divided into three main jobs, as follows:
Job I.

- Engineering, Design, Inspection,
Construction, and Procurement

Job II

- Operation and Management of
the EPG

Job III - Maintenance of the EPG
The various modifications to the contract

made during Operation HARDTACK,Phase I,

were as follows:

Modification 55, dated 29 June 1956, ef-

fective 1 July 1956, restated the entire contract
with new Appendices A and B.
Modification 56, dated 7 September 1956,

effective immediately, increased the “Obligated
Funds” available for use under the contract.

Modification 57 was not applicable to this
Operation.
Modification 58, dated 27 December 1956,

effective immediately, deleted Part V of Appen-

dix A, revised paragraph 2, Article IV, of the
basic contract, and increased the “Obligated
Funds.”
Modification 59, dated 31 December 1956,
effective 1 July 1956, revised Appendix A, firmed
and enlarged the scope of work of Job I, and
stated the estimated cost for the procurement of
equipment for FY 1957 and the estimated cost
of Jobs II and III for the six months ending 30

June 1957.

Modification 60, dated 24 June 1957, effective immediately, amended paragraph 2 of
Article IV of the basic contract to mcrease the
“Obligated Funds” available.
Modification 61, dated 1 August 1957, ef-

fective 1 July 1956, revised Appendix A by defining and increasing the scope of work under
Job I and by stating the estimated costs for
Jobs II and III for the 6-month period ending
31 December 1957 and the estimated costs for
procurement of equipment for FY 1958.

Modification 62, dated 15 August 1957,
effective immediately, amended paragraph 2 of
Article IV increasing the “Obligated Funds”
available.
Modification 63, dated 2 August 1957, effective immediately, amended and revised paragraph 5 of Article XXV to incorporate provisions
and requirements for work performed under the
contract within the scope of the Davis-Bacon
Act.
Modification 64, dated 19 September 1957,
effective immediately, amended paragraph 2 of
Article IV to increase the “Obligated Funds”
available.
Modification 65, dated 22 October 1957, effective immediately, increased the amount of

work under Job I of Appendix A.

Modification 66, dated 26 December 1957,
effective 1 July 1958, amended the contract to
permit the Contractor to use Government-owned
property in the performance of work in common
service departments where the cost is allowable
as an indirect item.
Modification 67, dated 17 February 1958,
effective 1 July 1956, revised Appendix A increasing the scope of work under Job I, stating
the amount of Government-furnished material to
be supplied and used by the Contractor in the
performance of Job I and the estimated costs
of Jobs II and III for the 6-month period ending
30 June 1958.
Modification 68, dated 10 February 1958,
effective immediately, amended paragraph 2 of
Article IV to increase the “Obligated Funds”
available.
Modification 69, dated 22 April 1958, effective immediately, amended paragraph 2 of
Article IV to increase the “Obligated Funds”
available.
Modification 70, dated 20 June 1958, effective immediately, amended paragraph 2 of
Article IV to increase the “Obligated Funds”
available.
,
Modification 71, dated 9 August 1958, effective 1 July 1956, increased and defined the
scope of work under Job, I, stated the amount

of Government-furnished material to be supplied

Page 37