CHAPTER Ill, SECTION 6

SECTION 6
SUPPLY AND PROCUREMENT
PROCUREMENT.

secure the necessary bids for this service. Bids

The activities of the Home Office Project
Purchasing Department were directed by the

in this type of service, and on the basis of low
bid an award was made to Jerome F. Gould,

Chief Purchasing Agent, with the assistance of

a Purchasing Agent, Chief Expediter, and Shipping Agent in the performance of all project
procurement functions.

As all procurement functions were contin-

gent upon receipt of material requisitions, co-

ordination of activities of these groups was predicated on the required delivery date of the
material or equipment. To ensure arrival of material and equipment at Jobsite within the specified delivery date, various aspects were taken
into consideration: procurement lead-time, type

of material or equipment, and method of shipment.

Initial procurement action was started dur-

ing the late months of 1956, and the tempo in-

creased throughout 1957 with an extended work

week becoming necessary

during the latter

months of 1957 and extending through 15 February 1958.

During the build-up for construction and
scientific program, considerable emphasis was

placed on the “lead-time” allowed for arrival
of material or equipment at Jobsite. Because
of the heavy volume of procurement and the
short delivery lead-time during this period, it was
necessary to solicit bids on very short notice by
telephone, telegraph, and letter request for quo-

tations. Although the element of time placed
undue pressure upon vendors, in most instances

were solicited from nine companies specializing

Inc., Brooklyn, New York. Partial dismantling
of the complex equipment was accomplished by
several H&N Communications Engineers. Upon

final dismantling, packing, and crating operations, all items were placed in storage at Stewart
AFB, pending arrangements for special MATS
airlift to EPG. Actual loading of the first of
six C-124 aircraft commenced on 5 August 1957;
the final aircraft was loaded on 9 August 1957.
Due to the long-lead time requirement for

distillation units, early procurement action was

initiated to assure the best possible delivery. At
the time of Purchase Order award there appeared

to be no difficulty in obtaining all required basic
materials and components. However, during the
process of manufacture, the sub-vendor furnish-

ing the compressors was absorbed by another
firm. This change caused numerous production
delays, and it became necessary to assign a representative at the factory to expedite production

to conform to required delivery schedules. During this delay period, other component parts
were delivered and with the cooperation of the
prime vendor, fabrication and assembly proceeded

and a minimum of time waslost. In spite of the

unforseeable delay, this order was completed in
a satisfactory manner.

Due to a change in Users’ requirements, the

delivery schedule of the mobile launching tower

all requests for quotations were processed in

for Station 6001 was accelerated by 30 days.
In order to accomplish this requirement, neces-

The early receipt of requisitions for items
of long lead-time and special fabrications such

a premium proposal to be submitted and accept-

the allowed period of time.

as steel towers, guys, bridge cranes, submarine

and telephone cables, steel piling, winches, distillation units, walk-in refrigerators, steel and
aluminum buildings, dehumidification and air
conditioning units, generators, and other mis-

cellaneous items, assisted greatly in allowing additional procurement time.
During May 1957 the Purchasing Depart-

ment was required to make the necessary arrange-

ments for dismantling, packing, crating, and
hauling of two Tropospheric Scatter Systems
which were transferred to the AEC from the U.S.
Air Force on an M/R basis. One unit was located
at North Truro, Massachusetts, and the other
at Stewart AFB, Newburgh, New York. A representative was sent to the Eastern seaboard to

sary details involving production, delivery of
component parts, and overtime required were
coordinated with the fabricator. thus enabling

ed. The final result was delivery of all compo-

nents two days earlier than required by the
revised delivery date.
During the early part of 1957, a Purchase

Order was placed for a dial telephone system
for inter-atoll communications. The original de-

livery was scheduled for the latter part of 1957,

but increased User requirements and necessary
design changes created a delayed delivery schedule. However, delivery of certain basic portions

of the system was expedited for earlier ship-

ment, enabling Jobsite to proceed with theinstalation.

The late 1957 and early 1958 requirements

covering pipe assemblies, caissons, and related
Page 373

Select target paragraph3