>i
CHAPTER 11, SECTION 5

(Neg. No. W-V-285-2)

Figure No. 2-142.

DOD Laboratory Building 582, Fred —
98% Complete.

authorization for the extension of the runway,
work wasstarted on the rehabilitation of portions
of the existing runway requiring repair. Stockpiling of materials for the project was started

on 16 January 1957, with all aggregate being
furnished by the Elmer plant. Initial work on
removing old pavement was started by ripping
out parts of Blocks 6 and 7. Joints removed
were cut straight and vertical. Following removal

ditional parking aprons were made in 8-inch
lifts and compacted to the specified degree with
grid and rubber-tired rollers, and watered to
optimum moisture content. When proper elevations were reached, a 6-inch sub-base course
was applied and compacted, followed by a 4-inch
base course of 2-inch-minus coral aggregate com-

pacted to 95% CBR. Concrete pours for the

base was recompacted to a 50% CBR value. A
4-inch crushed, graded base course was then
placed and compacted to 80% CBR.A seal coat

airstrip averaged about 400 cubic yards daily.
On 3 April 1958 the cross-over taxiways and
parking aprons were completed, with the latter
having 159 more aircraft tie-downs than were
included in the original plans.

sisted of 4 gallon of asphalt emulsion per square
yard of surface; beach sand was then applied,

tended for a distance of 395 feet, and the north-

of the old pavement and base course, the sub-

was applied over the base course, which con-

rolled, and broomed. The 24-inch surface
course was made up of 87% aggregate, 8% fine
beach sand, and 5% filler. Aggregates were all

graded crushed rock, and thefiller was made up

of 62% mineral rock dust and 30% portland
cement.

Preliminary work on the runway extension
project started in October 1957. Prior to this
date a study was made at Jobsite to determine
the quantity and types of materials required
for fill and hydrographic surveys of the Elmer
and Fred lagoon areas and to determine concentrated material locations. As a result of this
study, a Sauerman dragline was installed at
Fred to scoop material from the lagoon floor for
use as a fill under the sub-base; all graded ag-

The southwest end of the runway was ex-

east end extended 1220 feet. Sloping concrete

over-runs were poured at both ends of the runway, with a retaining sea wall formed and poured
to protect one corner of the southwest extension.
An entirely new runway lighting system was

part of the extension project, including runway
marker lights, warning and threshold lights,

a new regulator for control of the system, and
floodlights on the parking ramps. A new surfaced road along the ocean side of the runway
was also an additional airfield improvement.

gregates were produced and hauled from Elmer.
A sea wall, 855 feet in length, was constructed
to retain the extension fill at the northeast end

of the runway. Holes were drilled and blasted
which provided a start for pile driving; a total

of 91 bearing piles were driven to a 20-foot mini-

mum embedment. Following piling emplacement,
ore-cast concrete blocks were set and bolted to
she piles and then grouted in. A concrete cap

was then laid atop the entire length of the re-

taining wall.

Earth fills of the runway extension and ad-

(Neg. No. W-V-160-9)

Figure 2-143. Concrete Spreading at West
End of Airstrip — Fred.
Page 283

Select target paragraph3