SECRET
This material contains information affecting the
national defense of the United States within the

CHAPTER I, SECTION 1

meaning of the espionage laws, Title 18, U.S.C.,
Secs. 793 and 794, the transmission or revelation

of which in any manner to an unauthorized person

is prohibited by law.

CHAPTER|
INTRODUCTION
SECTION |
NARRATIVE SUMMARY

BACKGROUND.
Operation HARDTACK, Phase I, was the
fifth consecutive test series to be conducted at
EPG in which Holmes & Narver, Inc., participated as Architect-Engineer-Construction-Management Contractor for the Atomic Energy Commission. The Operation was by far the largest,
both in terms of area and of over-all scope of
operations required for the support of all elements of the Task Force. Although a considerable
portion of the required services were routine,

Operation HARDTACK demanded the utmost
in technical and administrative know-how, in-

genuity, and coordination to bring its operational
efforts to a successful conclusion.
Two outstanding accomplishments during
HARDTACK which called forth all experience
gained on previous operations at EPG were the
major installations on Site Yvonne for the
CACTUSevent andtherelocation of the ABMA
facilities from Bikini Atoll to Johnston Island.
Prior to December 1957, the scope of work
at Site Yvonne was limited to a major modification of Station 1310 and the rehabilitation of
several smaller stations; however, criteria were
received in December 1957 for a major installa-

tion, including a Ground Zero Station, pipe
arrays, major modifications to existing structures, and the construction of a number of new
Scientific Stations, which were to be completed
in sufficient time for a~-test event on 1 May

1958. When this requirement became known,
an all-out effort was exerted and through the

combined forces of Home Office and Jobsite
Engineering, logistics, and Construction, it was
possible to complete construction and to advance
the required ready date.

Whenfacilities were practically completed
for the ABMA program on Site How on Bikini
Atoll, a change in plans shifted operations 1745
miles eastward to Johnston Island. A set of
duplicate facilities was necessary there, requiring

the dismantling and re-erecting of a service

tower and various rocket launchers, removing
and re-installing User equipment, and transporting a mountain of supplies, materials, and
equipment to the new site. In a like manner,
this project was completed and made available

to the Using agencies well in advance of the
required dates.

Of the 37 HARDTACK test events for
which preparations were made, 4 were Ground
Zero Stations, 2 were underwater, 1 was a balloon
event, 2 were high altitude missiles, and 28
were afloat stations: 23 barges and 5 LCU hulls.
Two barge events were cancelled after comple-

tion of construction. As indicated, the zero stations used in the Operation were predominantly
afloat. This, in addition to unforseeable support

requirements for the underwater events, required
the increased use of marine craft and services
which at times taxed the Contractor’s capabilities to the limit, but in the final analysis all
requirements were adequately filled.
Experience gained from Operation REDWING indicated that radical changes and im-

provements, both organizational and administrative, would be necessary in order to provide for

more efficient conduct of operations for future
test series the size of REDWING orlarger.
Chiefly among these changes was the re-organization of certain Jobsite Divisions; the major
change was thecreation of the Communications
Division, placing all Communications operations

and maintenance responsibilities under one
Division Head. Other changes included the elimi-

nation of the Administrative Division, and the
transfer of Air and Land Transportation, Secu-

rity, Guard, Safety, and Rad-safety functions to
the Industrial Relations Division; the transfer
of marine, power, and distillation maintenance
functions from the Service Operations Division
to the Construction Division; the addition of a
Construction Manager, and the appointment of
General Superintendents as heads of construction and maintenance functions in the Construction and Maintenance Division. An Assistant

Resident Manager was designated as Executive
Division Head, to whom wasassigned theoffice
services and administrative functions. Material
take-off functions were transferred from the
Engineering Division to the Supply Division.
In addition to the divisional changes, other

functions within divisions were given departmental status in keeping with added duties and
responsibilities. As in REDWING,Bikini Atoll
was supervised by an Assistant Resident Manager responsible for the conduct of operations
connected with that atoll.
Along with this re-organization, a revamping

and streamlining of policies and procedures were
Page 17

SECRET

Select target paragraph3