CHAPTER II, SECTION 2 SECTION 2 CONSTRUCTION The Construction and Maintenance Division was responsible for the construction of all buildings, scientific structures, facilities, roads, and utility systems at EPG as authorized by approved Work Orders. It was also responsible for pro- Two typhoons in late 1957 caused damage to some structures on both Bikini and Eniwetok work for all departments and User agencies. Atolls, but in general, climatic conditions had no adverse effects on the construction program; rainfall conformed to the averages of the past five years. Oceanic conditions and tides limited the working time on the reefs and on a number During construction periods a General Superintendent was assigned to Bikini Atoll, of occasions prevented the off-loading of materials and equipment. Superintendents assigned to various sites. In necessitated the removal, relocation, and even viding Jobsite mechanical and machine shop where he acted as the field liaison representative of the Division. Assisting him were Construction Last minute changes in barge criteria often addition to construction responsibilities, these the deletion of certain installations, but in spite management of their sites and for observance of established safety and security rules and regulations. the Using agencies as they were required. UCRL barges were delivered to Bikini by LSD or by Navy tow. One barge being towed to Bikini was The first construction project of any appre- and another was partially sunk while in tow; Superintendents were responsible for the over-all ciable size in 1957 was the rehabilitation of airfield paving on Site Fred, which is covered in detail in Section 5 of this Chapter. Personnel strength started to increase in April 1957, with skilled workers requisitioned on the basis of a steadily increasing number of projects. A total of 429 men were assigned to the Construction and Maintenance Division by June 1957, of which 148 were assigned to the newly-opened Nan camp. Work started on a large concrete structure, Station 1312, on Site Janet on 9 Sep- tember 1957, shortly before the opening of that camp in October; by January 1958 construction of many Scientific Stations was in progress, re- quiring 988 construction workers on the job. The personnel peak was reached during the week of 8 April 1958, with 1338 men assigned to the Division. Even with this peak of construction person- nel, the priority completion of a numberoffacili- ties in the PAC program, the existing heavy work load on the Scientific Stations, the late receipt at Jobsite of design changes, and certain material shortages resulted in the necessity for a strictly controlled overtime policy to meet certain of the construction schedules. As facilities were completed, workers were either returned to their points-of-hire or transferred to other jobs requiring their skills. Roll-up of the tempory camps resulted in the further reduction of construction personnel. By 1 June 1958, the Division’s personnel strength was reduced to 934 men, of which 163 were working on the Johnston Island project.At that time the program was enlarged and Work Orders were received for additional Scientific Stations on Eniwetok Atoll, including 7 additional scientific barges and LCU hulls. of these problems, the barges were delivered to damaged when heavy seas were encountered, the latter was recovered, placed in drydock, and rehabilitated. Prefabrication methods were used to the utmost for both wooden and concrete structures, including re-inforcing steel, which was cut and shaped at Elmerfor all jobs. Concrete placement forms, building sections, barge device cabs, and helium tunnels were prefabricated at Elmer and at temporary camps for delivery to required locations. Submarine cable vaults, pump houses and sumps, small slabs, anchor blocks, etc., were poured at centralized locations and delivered where needed. Materials for the temporary camp- sites and Weather Stations were precut at either Elmer or Nan. At the time construction was started on the temporary camps, there was a combined inventory of 59,864 cubic yards of aggregate of all sizes stockpiled at Elmer, Fred, and Nan. This quantity was supplemented by producing an additional 58,813 cubic yards from 21 July 1957 through 18 May 1958. At the end of that period, there was an inventory of 51,791 cubic yards of all sizes stockpiled, indicating that 66,886 cubic yards of aggregate were used at all locations through 18 May 1958. As camps were opened, primary and secondary crushers were installed at Elmer, Janet, Nan, and Oboe. Elmer produced all aggregate used on Yvonne, while the Janet plant served the other islands in the northern part of Eniwetok Atoll. Nan produced what aggregate was required at that site and the northern islands of Bikini Atoll, and the plant at Oboe supplied the needs of the Tare Complex and the other islands on the west side of Bikini Atoll. Page 63

Select target paragraph3