see a
be md eee ce ee WSnanthel ade
deltasbeidal aihon'sWicis 1bae caeSots

PART Ill, CHAPTER 13

CHAPTER 13
FUNDING AND ACCOUNTING
13.1

structure, and that specific structure

The major financial problems encountered
during peration HARDTACKwere:

a.

Thereceipt of Plant Acquisition and
Construction funds was in conflict
with the operational period. The bulk
of major additional and replacement
permanent construction had to be
accomplished concurrently with the
scientific test facilities. This contributed to excessive peaking manpower
requirements and the diversion of
much needed construction stores to
permanentplant instead of to scientific construction.
!
Current-use stores invéntory levels
were too low preceding the start of
Operation HARDTACK. The Contractor’s cost ceiling limitations on

inventory levels made it impossible to
stockpile sufficient long lead-time and
scarce materials. This contributed to
“crash” procurement, expensive airlift, and the disruption of construction planning schedules pending
receipt of key materials.
Discrepancy in the Contractor's cost
of installed equipment was noted
early in the Operation, but it was too
late to effect a correction during the
Operation. Equipment procured for
a particular structure or facility was
charged to that structure or facility,
despite the fact that subsequent planning may have deleted the requirementfor the installation of the equipment. The equipment that had been
charged but not installed was then
available for installation in a different facility at no charge to that pro-

will be charged with the cost of all
such items.

13.2

tions, this report had

created gross overstatement of costs
in the first instance and equally gross
understatement of costs in the latter
instance. This problem was subse-

—Expendable Test Construction and Test Site

Operations, was instituted. The principal purpose of this report was to associate cost with the
scientific participant responsible for the cost. To
this end the report has proved successful, particularly in disclosing to the Users the varying
costs of providing temporary campsandauxiliary
facilities, including operation and maintenance.
13.3.

Based on data furnished the Manager,
ALO, by the participating organizations,
a report has been compiled covering the ALO
cost for test construction and test site operations
in connection with AEC participation in Operation HARDTACK, Phase I. This report is presented herewith as Fig. 3-10, Summary by Cost
Budget Category, and is supported by Figs.
3-11A-C, Expendable Test Construction and
Test Site Operations.

13.4

drawn for installation in a specific

Fig. 3-10 reflects the ALO 3000 Program

full-scale activity and related reimbursable work costs by organization and by the fol-

lowing major cost categories:

3831 Expendable Test Construction
3832 Test Site Operations
13.5

Costs supporting Fig. 3-10 reflect further
breakdowns of cost as follows:

Fig. 3-11A — Expendable Test Con-

struction detailed by major items

quently corrected by establishing an

inventory of equipment, normally
considered as installed, which will be
charged with the cost of all the
equipment on hand (not physicall
installed) and subsequently procured.
The inventory will be credited with
the value of the equipment with-

been compiled by the Los

Angeles Office of the Contractor. By moving the
responsibility for compiling and issuing this report to Jobsite through the critical construction
stage, information was available to participants
as much as three weeks earlier than during previous operations. Also, as shown in Figs. 3-11A-C,
a new report, entitled Cost and Estimate Report

ject (considered as Government Fur-

nished Equipment). Obviously, this

For Operation HARDTACK,considerable

progress was made in expediting the publication and circulation of timely test construction
Cost and Estimate Reports. For
previous opera-

or types and by Users
Figs. 3-11B & C — Test Site Operations detailed by subfunctions and
by Users

13.6

Also included are two charts which present graphically the relation of certain

cost factors to population factors. The data used

Page 67

Select target paragraph3