eae eb ro Shee te lee aller eeeUM Thodaeee ke

PART If!, CHAPTERS 3 and 4
struction of a poured concrete IBM building
with suspended acoustical ceiling, removable
floor panels supported on stringers, and a major
utilities plant to provide air conditioning both
overhead and underthe floor. Two guest houses
were erected on Site Elmer to accommodate
visiting dignitaries. The base facility construction program also included a Butler-type administration building to house the Contractor’s offices, concrete and prefabricated aluminum
barracks, warehouses, community service
buildings, and several laboratory buildings. The
Administration Compound was enlarged and
provided with aluminum chain link fencing. A
large volume of modifications to existing structures and additional construction was accomplished to provide some measure of comfort to
Task Force personnel. For example, eight barracks were modified to provide day rooms, and
newly constructed barracks included day rooms.
Building construction on Site Fred was
predominantly Pasco-type structures for warehousing. Ten major concrete projects on Site
Fred included the airfield extension, a 200,000gallon

water

storage

reservoir,

an

explosive

storage building, two pumphouses, three concrete ramps, a double tennis court, and a decontamination storage building.

Additional recreational facilities, such as

volleyball and basketball courts, were constructed
on Sites Fred, Elmer, and Nan.

MAINTENANCE
3.4

H&N wasresponsible for the maintenance
of all buildings, grounds, utilities, and all

AEC-owned equipment. Although somewhatcurtailed by the construction effort, the maintenance

program was continuous throughout Operation
HARDTACK, Phase I, and was predicated on
preventive maintenance, normal wear and tear,

and non-scheduled repairs. Due to the critical
requirement for continuous operation, reefers,

generators, and pumps were checked daily, and
any breakdowns were cause for immediate repair, day or night. All construction equipment
was rigidly scheduled for lubrication and inspection, and breakdownswere often forestalled
by timely replacement or overhaul of parts.
Preventive maintenance with respect to buildings
and structures included securing all doors and
shutters in an open position to prevent shockwave damage during test events.
During the operational phase, H&N was
also responsible for the preventive maintenance/—
and minor repair of all Military-owned vehicles,
except those located at Site Fred.
—
The maintenance and repairs to marine
craft was confined to engines, bottom and hull
plating, replacement of stringers and stiffeners,
and the replacementand repairs of propellers and
shafts. These repairs were accomplished by

either beaching the craft by use of a “Gilhoist”

or placing the craft in a floating dry dock.

The maintenance of utilities increased
proportionally with the increase in population
during the build-up period, when additional facilities were put into use.

CHAPTER 4
s
ENGINEERING, CONSTRUCTION, AND
MAINTENANCE OF TEST FACILITIES
GENERAL
‘4.1

‘The increased scope of Operation HARD-

TACK, Phase I, nearly twice the magnitude of Operation REDWING,required a heavy
expendable test construction Rrogram for both
Bikini and Eniwetok Atolls. Criteria for scientifie structures were not completely released by
the Laboratories until the middle of January,
1958. The procurement of men and materials and
the task of transporting them to the EPG

created multitudinous problems for the AEC

Contractor. Material storage, fabrication, construction, and inspection, as well as the housing
and feeding of construction personnel, are but
a few of the manyefforts that result in a completed structure. Despite the many obstacles and
the rigid construction schedules, the job was
effectively accomplished by H&N.
Page 44

42

To maintain a dual-shot capability,
UCRLtest facilities were constructed at
Bikini Atoll and LASLtest facilities at Eniwetok
Atoll. However, adverse weather conditions in
the Bikini Atoll area resulted in the transfer of
five shots to Eniwetok Atoll. Twenty-four barge
zero stations and five LCU hull zero stations

were fabricated for Operation HARDTACK,

Phase I, using cargo-type barges and obsolete
Navy and Army
LCU hulls procured from
sources. Subsequent to construction completion,
one of the barge zero stations was damaged
beyond repair while in tow from Eniwetok to
Bikini Atoll, and two were cancelled as a result
of a program change. Barge station construction
required the addition of a second floating dry
dock (AFDL) at Eniwetok Atoll and the construction of a three-fingered barge slip at Site

Nan. Of the shots scheduléd for Operation

ne

ee

KETTECLELETTEHEEHEETTEE EEE EE

pre

Select target paragraph3