BUILDING #10 - RAWINSONDE TOWER: This structure was almost totally destroyed. Two of the four piers for the tower could be utilized in rebuilding the structure. However, the platform donsisting of two Navy Cubes with concrete cap is not usable. GENERAL: The sewer outfall appears te be still in usable cmdition. Both antennaes are in very good condition. Provision should be made to furnish several rolls of screen, several lengths of various size pipe, and some lengths of different size cables. At 1510 the writer and Mr. Bush departed Kapingamarangi Atoll and arrived at Ponape at 1800 hours. On April 10, 1957 and inspection was made of the weather station in Kusaie after the party had landed there at 1100. The following will be required to place the weather station in an "as-built" condition for occupancy. BUILDING #1 - SUFFLY & OPERATICIS: Needs new screens throughout, and replacement of two doors. BUILDING #2 - GENERATOR SHED: In good condition. Requires routine cleanup prior to equipment installation. BUILDING #3 - RAWINSONDE TOWER: Base and tower in good condition. Ready for equipment installation. BUILDING #4 - PIT LATRINE: Should be entirely replaced. ° BUILDING #5 - FUEL TANK BASE: In good condition and ready for piping equipment. BUILDING SITE "e" PUILDING #1 - REEFER BANK: In good condition. Needs normal cleanup prior to equipment installation. BUILDING #2 - MESS HALL: Fifty percent (50%) of the screening needs to be replaced, the remainder brushed and cleaned,

Select target paragraph3