Meeting #1789, 18 October 1961:
ti
v
wet “
ne
The Commission discussed at some length the question of construction
management at NTS and a recommendation for selecting a contractor
to perform these services.
Meeting #1790, 26 October 1961:
In a discussion of budgets for weapons programs,
Betts noted that the
FY 63 budget estimate first submitted had been made in the absence
of specific weapons requirements and thus was just made to be
as the FY62 estimate.
the same
DMA had now changed their estimate to 340 million
from 289 million and a very recent review had upped that estimate
to
350 million.
Meeting #1792,
31 October 1961:
A discussion at this meeting addressed ''Disarmament policy '''
a new proposed disarmement plan submitted by the
the AEC's opinions.
ACDA,
reviewing
requesting
The document in the files here in the AEC which
addresses this is AEC 226/300.
Meeting #1802,
21 November 1961:
It was discussed that the pipe fitters and the operating engineers had had
a disagreement at the NTS and the former group had established a strike
picket line which certain other unions have refused to cross.
Luedecke
noted that as a result of this strike, the weapons test program will be
seriously effected and the Rover Project will be delayed ona day per day
basis as long as the strike goes on.