FRENCH FRIGATE SHOALS
F & S NO.
22003
TITLE
Vertical Soundings of the Ionosphere - Subtask A616
USER
STRUCTURE, FACILITY NO.
TC
SCIENTIFIC STATION NO.
None
93-3-3
FUNDING
AGENCY
($000)
DASA /
PRE-GO
EAO 1106-|
4101-61
POST-GO
Estimate 12/65
30.7
30.7
TOTAL
30.7
30.7
RDT&E
ENGR
gop
PROC
CONST
GO+130
FODGO+160
TOTAL
FURN
Engineering costs included in F&S Number 21004.
PRIOR YEARS
ENGINEERING Completed.
Drawings:
93-002-C2
93-3-3-Cl and El
POST -GO
PROCUREMENT
To be accomplished.
CONSTRUCTION
Test Command will furnish all antennas and one instrument
trailer 8 x 36x 10-ft. high.
Contractor will furnish the following: a) two 60-ft.
and two 80-ft. poles; b) one 100 gallon water tank;
ities; and,
c) latrine and sewage facil-~-
d) two 30 kw, 120/208 volt, 60 cycle, 3 phase generators.
One of
the generators is utilized as a back up power source.
The contractor will perform the following: a) the two 80-ft. poles will be erected 860-ft. apart and the two 60-ft. poles will be placed on a line offset 18-in.
from the line connecting the 80-ft. poles; each 60-ft. pole will be 188-ft. from
the center point between the larger poles; b) install TC furnished antennas on
the poles; c) site the instrument trailer; d) install water tank and provide
water for photographic processing; e) install generators with automatic switchgear; f) install septic system for sinks and toilet; and, g) provide electrical
hookup where required. Refer to Figure A-19, Appendix A, for site location.
Two scientific personnel are assigned to Subtask A616 at this location.
22-5
in * ad | |
VOLII