SECTION IX
COST ESTIMATE

SCOPE:
The estimates presented for work under Phases I, II and IIT cover facilities as recommended in this Revort and summarized in Section VIII.

These

estimates include all anticipated expenditures in connection with engineering
and construction, except the Architect-Engineer-Construction=Management

(AECM) fee.
The estimates for Phase IV and V are developed to include all AERCM costs
based on operation under the assumptions listed below.

Basis of time schedule

is:

Phase IV=£A, Experiment

Dec. 1950 through March 1951

Phase

April 1951 through Dec. 1952

V-A, Roll-up

Phase IV-B, Experiment

Jan. 1953 through April 1953

Phase

May 1953 through Aug. 1953

V-B, Roll=up

It is assumed that during Phase IV, the Los Alamos Laboratory will statien not over 250 people in the camp on Parry and on the shot islands and
that the ACM contractor will assign 100 mechanics and helpers to work under
their direction.

In addition, approximately 250 others will be required to

operate the utilities and facilities.

During Phase IV, A and B, the additional services. furnished include purchase, preparation and serving of food; operation and housekeeping of rooms,
offices, etc.; medical, laundry, barber, sales store and recreation services;
maintenance and operation of utilities, including telephone operators; local
air, water and motor transportation for personnel and supplies; light stevedoring and warehousing of "Laboratory" supplies; fire protection.
During Phase V, A and B, the services furnished include stationing a

xX-1